Pumped Storage Plant Guangzhou, China

The Guangzhou Phase II pumped storage plant in Guangdong province utilises the storage capacity of the existing upper and lower reservoirs of Guangzhou Phase I. The new (Phase II) works include the construction of an intake structure at the upper reservoir, upstream and downstream waterways, surge tanks and a power cavern.

Client                                                                   Guangdong Pumped Storage Power Station Joint Venture Corporation (GPSJVC)
LocationChina
Services Period1994 – 2000
Technical Data
  • Number of Pump turbine
4
Turbine operation 
  • Rated power
4 x 306 MW
  • Rated discharge
4 x 64.85 m³/s
  • Rated net head
512 m
Pump operation 
  • Power
4 x 308 MW
  • Rated discharge
4 x 50.6 m³/s
  • Max. total lift
552.8 m
Effective reservoir volume
  • Upper reservoir
16.84 x 106 m³
  • Lower reservoir
17.11 x 106 m³
Pressure tunnel, D/L9.0 m / 950 m 
Penstock, D/L8.5 m / 1,270 m 
Tailrace tunnel, D/L9.0 m / 2,000 m
Services Provided
  • Consultancy services during project review
  • Tender evaluation
  • Contract negotiations
  • Approval
  • Workshop test
  • Implementation and site supervision