Modernisation and Upgrading of 6 Hydro Plants, India

After some 20 and more years of continuous duty, the six hydro plants Chibro, Khodri, Dhakrani, Dhalipur, Kulhal and Tiloth approached the stage where rehabilitation of plant and equipment had become necessary in order to restore operational reliability and adjust the plant systems to the current state-of-the-art.

Client Uttarakhand Jal Vidjut Nigam Ltd. (UJVNL)
Location India
Services Period 2008 – 2009
Technical Data
  • Chibro HEPP: Installed capacity 4 x 60 MW at 110 m head
  • Khodri HEPP: Installed capacity 4 x 30 MW at 57.9 m head
  • Dhakrani HEPP: Installed capacity 3 x 11.25 MW at 19.8 m head
  • Dhalipur HEPP: Installed capacity 3 x 17 MW at 18 m head
  • Kulhal HEPP: Installed capacity 3 x 10 MW at 18 m head
  • Tiloth HEPP: Installed capacity 3 x 30 MW at 147.5 m head
Services
  • Inception study
  • Feasibility study
  • Tender documents

Project Search