Independent Engineering Services for 70 MWp PV Salvador Project, Chile

Lahmeyer has been assigned to take the role of Lender’s Engineer for the PV Salvador Project.

The project is located in the Atacama Desert (Chile) and consists of 70 MWp of c-Si modules, mounted on single-axis tracking structures, both provided by SunPower, and outdoor inverters.

Lahmeyer has performed a full technical Due Diligence (leading to a successful financial close) and is currently monitoring the construction phase.

LocationChile
Services Period2013 – ongoing
Technical Data
  • Solar resource:
over 2,300 kWh/m2.a
  • Grid connection:
110 kV
  • Design:
-Si modules, single-axis tracking
Services
Full technical Due Diligence including:
  • Site assessment
  • Technology and design review
  • Solar resource and yield assessment
  • Implementation Plan review
  • Contractual review
  • CAPEX and OPEX review
  • Grid connection review
  • Permitting review
  • IFC’s performance standards compliance
  • Risk evaluation
Construction Monitoring:
  • Monthly reporting
  • Periodic site visits
  • Drawdows certifications