Engineering Surveying and Quantity Surveys at the Merowe Dam Project
Provision of all topographic construction services required throughout the various project phases and conduction of control measurements to ensure quality and accuracy.
Client:
Dams Implementation Unit (DIU), Republic of Sudan
Period:
2003 - 2009
Services:
- Survey works during the various construction phases
- Adjustment of horizontal and vertical network
- Execution and supervision of various ground surveys
- Setting-out surveys
- As-built surveys
- Digital calculation and evaluation of all survey works
- Training of local staff
Technical data:
- Engineering, supervision and project management of a 9.76 km long and 65 m high dam about 350 km north of the capital Khartoum, downstream of the 4th Nile cataract