Energy Interconnection between Malta and Central Europe
The Government of Malta aims to supplement and enhance the existing power supply infrastructure on the island in order to secure reliable energy supplies for the next decades.
Among the various projects under consideration, a new cable inter¬connection between Malta and Sicily receives spe¬cial atten¬tion. Further options to en¬hance energy supplies in the long run include capa¬city add-ons in thermal power generation based on fuel-oil and/or natural gas brought to the island eit¬her via a new pipeline or as LNG/CNG.
Among the various projects under consideration, a new cable inter¬connection between Malta and Sicily receives spe¬cial atten¬tion. Further options to en¬hance energy supplies in the long run include capa¬city add-ons in thermal power generation based on fuel-oil and/or natural gas brought to the island eit¬her via a new pipeline or as LNG/CNG.
Auftraggeber:
Malta Resources Authority (MRA)
Ausführungszeitraum:
2007 - 2008
Leistungen:
- Load Projections under consideration of the Mid-term National Energy Efficiency Plan
- Technology Screening regarding most promising Energy Supply Options
- Review of Price Projections for possible primary and secondary Energy Sources
- Review of the Regulatory and Legal Framework
- Identification and Definition of Supply Options
- New Generation Options
- Rehabilitation, Modernisation and Conversion of Existing Power Plants
- DC High Voltage Interconnection to Central Europe
- Gas Supply Options (CNG, LNG and Pipeline)
- Development of Optimal Expansion Plan
- Examination of Power Supply System Expansion Scenarios
- Simulation and Operational Optimization of Generation Facilities’ Dispatch
- Evaluation of technical, economic and environmental aspects
- Determination of the optimum power supply system development plan